
|
Partner John Mrowiec authors the monthly law column for Midwest Construction, a McGraw-Hill publication. The magazine’s audience is owners, developers, contractors, design-builders, construction managers, engineers, architects and construction suppliers in Illinois, Indiana and Wisconsin. The subjects of the articles have included: |
- Construction Manager’s Increases to Original Lien
Claim for Continuing Work Did Not Prime Mortgage
Lien, June, 2008
- Clause on Out-of-State Venue for Arbitration Survives Statute, May, 2008 (View article)
- Seeking Remedies to False Representations, April, 2008 (View article)
- When Is a Written Construction Contract Effective?, February, 2008 (View article)
- Highlights of the Newly Revised Owner-Architect Agreement., January, 2008 (View article)
- What are the Changes in AIA’s General Conditions Contract?, December, 2007
(View article)
- Illinois Enacts Private Project Contractor Prompt Payment Act, November, 2007
(View article)
- Contracts and ‘Cardinal Changes’, October, 2007 (View article)
- Follow Terms of Contract and Bond Both, September, 2007 (View article)
- Beware of False Claims on Public Contracts, August, 2007 (View article)
- Might General Liability Insurance Provide Defense for a Defective Work Claim?,
July, 2007 (View article)
- Notice of Claims for "Constructive Changes", May, 2007 (View article)
- The Perils of Signing Progress Payment "Partial Waiver & Release" Forms Without Reserving Claims, April, 2007 (View article)
- Who's on the Whose Team with Alternative Delivery Methods?, March, 2007
(View article)
- Payment Bond Defines Claimants, Deadlines, February, 2007 (View article)
- "Reservation of Rights" in Surety’s Denial of Payment Bond Claim?, January, 2007
(View article)
- Termination by Owner After "Substantial Completion": Is It Inherently Wrongful?, December, 2006 (View article)
- May a Backcharge Always Include a Mark-Up? , November, 2006 (View article)
- The Risk of Long-Lead-Item Expenses , October, 2006 (View article)
- Financial Obligation Can Exist Even with Unsigned Contract, September 2006
(View article)
- Importance of Timely Change Orders Shown, August, 2006 (View article)
- Full Subcontractor Payment Defeats Lower Tier Sub's Timely Lien Claim, June, 2006 (View article)
- Baseless Motions to Vacate Arbitrated Awards Rebuked,
May 2006 (View article)
- Perils of Remedying Disputed Defective Design or Construction
April 2006 (View article)
- 'Conditional' and 'Unconditional' Payment Releases,
March 2006 (View article)
- Many RFIs Could be Insufficient To Recover Delay Damages,
February 2006 (View article)
- Sidestepping a General Contractor's Backcharge Backfired,
January 2006 (View article)
- Indiana Case Illustrates Dispute Resolution Clauses,
December 2005 (View article)
- Payment Bond Claimant's Recovery of Penalties Under Statutes Governing the Conduct of Sureties.,
November 2005 (View article)
- Quantifying the Relationship Among Overtime, Project Duration and Labor Productivity,
October 2005 (View article)
- Potential Liability Of Construction Escrowee To Owner For Unpaid Subcontractor Liens,
September 2005 (View article)
- Specifications’ Or Subcontract’s Listed Testing Method: Not Necessarily The Last Word On Meeting Performance Criteria,
August 2005 (View article)
- Construction Manager Held Not Liable To Suit For Acceleration Damages By Electrical Prime Contractor,
July 2005 (View article)
- Use Of The Modified Total Cost Methodology In The Context Of Multiple Changes And Delays,
June 2005 (View article)
- Concurrent Delays: The Importance of Apportionment,
May 2005 (View article)
- Quantifying the Impact of Change Orders,
April 2005 (View article)
- Quantifying the Impact of Change Orders,
March 2005 (View article)
- Contractors' Right to Assert Subcontractors' Claims Recognized,
February 2005
(View article)
- Could 'Accord and Satisfaction' Language Be Overcome?,
January 2005 (View article)
- Determining Who Breached a Contract First,
December 2004 (View article)
- So You Think Deleting E-mail Is a Good Idea? ,
November 2004 (View article)
- Failing to Sign Subcontract Before Accident: Prime Contractor Might Not Be
'Additional Insured' ,
October 2004 (View article)
- Must Payment to Customer in Bankruptcy Be Returned? ,
August 2004 (View article)
- Consequential Damages of Contractor's Lost Future Profits,
July 2004 (View article)
- Providing Unconditional Lien Waivers in Advance of Payment:
A Dangerous Practice in Wisconsin,
June 2004 (View article)
- Mechanics Liens on Multiple Structure, Multiple Owner Project,
May 2004 (View article)
- The Pitfalls of Mechanics Liens for Tenant Work,
April, 2004 (View article)
- Two Views of the Same Contractual Defenses On Increased Labor Cost Claims,
March, 2004 (View article)
- May a Mistaken Public Bid Be Withdrawn Without Penalty?,
January, 2004 (View article)
- Ambiguous Specifications:
The Federal Duty to Inquire, December, 2003 (View article)
- 'Best Value' Public Procurements:
Substantially Lowest Price Might Not Equal Winning Offer, November, 2003 (View article)
- Unrepresented Mechanics Lien Claimants Committed Fatal Errors, October, 2003
(View article)
- Ambiguous 'Arbitration' Provision Means Dispute must be Litigated, September, 2003 (View article)
- Electronic Discovery: Producing Electronic Documents in Litigation and Arbitration, August, 2003 (View article)
- Recovery of Unabsorbed Home Office Overhead
(Under the Eichleay Formula: The Standby Test)
, July, 2003 (View article)
- Payment Bonds and Arbitration:
Is the Surety Bound by the Result of a Claimant's
Arbitration with the Principal?, June, 2003
- Does an 'Incorporation by Reference' Clause
Always Include the Incorporated Contract's Arbitration Provision?, May, 2003
- Is Payment a Condition Precedent to Release Language in a Settlement Change Order?
, April, 2003
- The Problem of Proving 'Causation' of Damages, February, 2003
- Preserving Arbitration and Mechanics Lien Rights, January, 2003
- Forum Selection Clauses: Will Parties Be Required to Litigate or Arbitrate Distant from the Project Site?, December, 2002
- Construction Manager Unable to Dismiss Commercial End-User's Claims of "Consumer Fraud" and "Negligent Misrepresentation", November, 2002
- Arbitration Without A Consolidation Provision: Pickle in the Middle, October, 2002
- Fraudulently Overstated Mechanics Lien Claim Prevents Recovery, September, 2002
- Protesting Local Public Contract Bids: Who is the Lowest Responsive, Responsible Bidder? August, 2002
- Protesting Local Public Contract Bids: Who is the Lowest Responsive, Responsible Bidder? July 2002
- Termination for Convenience: Can An Owner Deduct Damages for Contractor's Breaches?, June 2002
- Illinois Power Court Upholds Design-Builder's Damages Limitation Clauses, May 2002
- Termination For Convenience: What May the Contractor Recover?,
April 2002
- Prime Contractor's Failure to Prove Reliance Allows Subcontractor to Escape From Bid, March 2002
- Construction Law: Prime Contractor Not Liable to Union Fund for Subcontractor's Failure to Pay Benefits, February 2002
- Conditions to Payment for 'Extra Work': The 'Prevention' Exception, January 2002
- No Damages for Delay" Clauses: Indiana Enforces Where Contractor Does Not Raise Typical Exceptions, December 2001
- Use of the "Modified Total Cost" Method of Damages Quantification, November 2001
- Signed Change Orders May Act As Releases, October 2001
- Federal Appeals Court Declares Local Government MBE/WBE Ordinance Unconstitutional, September 2001
- Conditions to Payment: Extra Work Prevention Exception, August 2001
- The Implied Covenant of "Good Faith", July 2001
- Void Indemnity Provisions and Insurance, June 2001
|
|